Humtso youth renew appeal to finish stalled Humtso-Elumyo road
Sanctioned in March 2024 for 18 months, the Wokha PMGSY-III road is in its second extension. The contractor's manager promises completion before next monsoon.

WOKHA – The Humtso Village Youth Organization (HVYO) has made a second appeal for work to resume on the Humtso-Elumyo road in Wokha district, a rural road sanctioned under the Pradhan Mantri Gram Sadak Yojana (PMGSY-III) in March 2024 for completion in 18 months. The project has since entered its second extension period without what the youth body calls “substantial progress”.
In a press release dated November 15 and seen by Nagaland.News, the HVYO said it met the manager executing the project, along with the Humtso Village Council and the site supervisor, and urged that the remaining works begin before the end of February 2027.
Humtso-Elumyo road: what has been done and what is pending
According to the release, earth cutting, Hume pipe culverts, protection walls and the excavation of side drains have been carried out on the Humtso-Elumyo road. However, it said the “critical components” of the project, FDR (full depth reclamation), PCC (plain cement concrete) and bituminous works, “are yet to commence”.
That means the road surface itself has not yet been laid, more than two and a half years after the project was sanctioned. The scheme, a centrally sponsored programme for all-weather rural roads. In September, a PWD sub-divisional officer took part in a review of the project.
Contractor’s manager cites monsoon, machinery shortage
HVYO members, the Humtso Village Council and Tsenpo Murry, described as the site supervisor, jointly met Dr John Murry at his residence on the morning of November 15. A group photo released by the HVYO is captioned 7:00 am, Sovima, Dimapur. The release describes Dr Murry as the manager executing the Humtso-Elumyo road project undertaken by M/s Chabou & Co.
Dr Murry cited several challenges, including an early and prolonged monsoon, a shortage of machinery and “other technical difficulties”, the release said. According to the HVYO, he gave a “personal commitment to commence the said project work at the earliest to ensure completion and inauguration before the arrival of the next monsoon”. Nagaland.News could not independently reach him or the firm for comment.
The HVYO said it “lauded” Dr Murry for his “unequivocal assurance” and urged that the remaining works begin before the end of February 2027, to leave enough time for completion within the promised timeline. It added that the people of Humtso village are prepared to extend necessary support and “earnestly anticipate” access to good roads.
First appeal in September set a Christmas target
The release is the youth body’s second appeal on the road. In early September, representatives of the HVYO, the Humtso Village Council, Tsenpo Murry, then described as the contractor’s representative, and PWD Sub-Divisional Officer Er Chandemo Tungoe met to review the project, The Morung Express reported. Nagaland Post and Eastern Mirror also covered the meeting.
At that meeting, the department said it was working to complete the road by March 2027, according to those reports, and the contractor’s side cited incessant rain and machinery shortages and breakdowns. The HVYO had then asked for a motorable road before Christmas. Two months on, its latest release says the surfacing works have still not started.
Delays on PMGSY roads have drawn complaints elsewhere in Wokha district too. This week, an advisor sought action against the contractor of the Sanis-Lakhuti road, a PMGSY-II road.
What is not yet known
The release does not give the sanctioned cost or length of the Humtso-Elumyo road, or the new deadline set under the current extension. It also does not explain the delay beyond the reasons cited by Dr Murry.
The PWD and the state government have not publicly responded to the second appeal. It is also not clear whether the March 2027 completion target the department gave in September still stands. Nagaland.News will update this story if the department or the firm responds.